Buildings and Facilities25OD0284

CONSTRUCTION OF MULTI-PURPOSE BUILDING (3S MAYSAN) PHASE 2, BARANGAY MAYSAN, VALENZUELA CITY

CONSTRUCTION OF MULTI-PURPOSE BUILDING (3S MAYSAN) PHASE 2, BARANGAY MAYSAN, VALENZUELA CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱14,353,503.15. Status: Past target date (DPWH On-Going). Contractor on record: RWORKMATE CONST. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Creeks of Amparo Subdivision, Barangay 179, Caloocan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-25-0017963

₱0.00 · FY2025

Released to Regional Office - IVB (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,353,503.15

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2025

Target End

October 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.