Buildings and Facilities23FK0122

CLUSTER LI- 1.) CONST. OF 2STY4CL SCHOOL BUILDING, PILAR NATIONAL COMPREHENSIVE HIGH SCHOOL, PILAR, SORSOGON 2.) CONST. OF 2STY4CL SCHOOL BUILDING, MARIFOSQUE ELEMENTARY SCHOOL, PILAR

CLUSTER LI- 1.) CONST. OF 2STY4CL SCHOOL BUILDING, PILAR NATIONAL COMPREHENSIVE HIGH SCHOOL, PILAR, SORSOGON 2.) CONST. OF 2STY4CL SCHOOL BUILDING, MARIFOSQUE ELEMENTARY SCHOOL, PILAR is a DPWH-tracked public work in Sorsogon DEO, Region V. Reported contract value: ₱35,879,747.56. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RMH CONST. Figures trace to dpwh.

Sorsogon DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure of Brgy. Siuton Flood Control, Magallanes, Sorsogon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Sorsogon DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱35,879,747.56

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

December 7, 2023

Target End

August 2, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.