Roads23K00176

CONSTRUCTION OF JCT. BUKIDNON - DAVAO CITY ROAD TO JCT. KIBURIAO - KITAOTAO RD (SAN JOSE - MINSALIRAC - SAN ISIDRO - MANUTO - MINSAMONGAN - KIBURIAO SECTION), QUEZON, BUKIDNON, PACKAGE 1

CONSTRUCTION OF JCT. BUKIDNON - DAVAO CITY ROAD TO JCT. KIBURIAO - KITAOTAO RD (SAN JOSE - MINSALIRAC - SAN ISIDRO - MANUTO - MINSAMONGAN - KIBURIAO SECTION), QUEZON, BUKIDNON, PACKAGE 1 is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱140,693,693.53. Status: Reported complete (DPWH). Contractor on record: RFB CONST CORP. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱140,693,693.53

Progress

Reported complete (DPWH)

Start Date

May 29, 2023

Target End

March 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.