Buildings and Facilities18DQ0105

CONSTRUCTION OF FOUR (4) STOREY TWELVE (12) CLASSROOM SCHOOL BUILDING AT NEW ERA NATIONAL HIGH SCHOOL, DASMARINAS CITY, CAVITE

CONSTRUCTION OF FOUR (4) STOREY TWELVE (12) CLASSROOM SCHOOL BUILDING AT NEW ERA NATIONAL HIGH SCHOOL, DASMARINAS CITY, CAVITE is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱40,056,276.62. Status: Reported complete (DPWH). Contractor on record: HAUSLAND CONST. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

234 projects · ₱9.5B total · 1 flags

Other projects by this contractor

No sat.

CONST OF FOUR (4) STOREY - ONE HUNDRED (100) CLASSROOM SB @ TAGAYTAY CITY, CAVITE

Cavite 2nd DEO, Region IV-A

2018₱208.9M
Reported complete (DPWH)
No sat.

CONST OF MPB (TENEMENT HOUSING), BRGY MAITIM EAST, TAGAYTAY CITY

Cavite 2nd DEO, Region IV-A

2023₱181.4M
Past target date (DPWH On-Going)
No sat.

FY 2018 DPWH INFRASTRUCTURE PROGRAM LOCAL PROGRAM LOCAL INFRASTRUCTURE PROGRAMNATIONAL ROADS AND BRIDGE NATIONAL ROADSROAD OPENING / CONSTRUCTION OF TAGAYTAY BYPASS ROAD, TAGAYTAY CITY, CAVITE

Region IV-A, Region IV-A

2018₱144.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - JUANITO R. REMULLA, SR. RD - K0035 + (-008) - K0035 + 109, K0035 + (

Cavite 3rd DEO, Region IV-A

2023₱127.8M
Past target date (DPWH On-Going)
No sat.

ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS / NEW ROADS GENERAL AGUINALDO-MAGALLANES -NASUGBU ROAD (EAST - WEST ROAD), PACKAGE 3, MAGALLANES-GEN. AGUINALDO SECT., CAVITE

Region IV-A, Region IV-A

2021₱127.0M
Past target date (DPWH On-Going)
No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM NETWORK DEV'T. PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS GEN. AGUINALDO- MAGALLANES- NASUGBU ROAD (EAST- WEST ROAD), AMADEO SECT., CAVITE

Region IV-A, Region IV-A

2020₱125.4M
Reported complete (DPWH)
View all 234 projects →

4. Implementation

Contract Amount

₱40,056,276.62

Progress

Reported complete (DPWH)

Start Date

December 27, 2018

Target End

October 17, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.