Buildings and Facilities23OG0070

CONSTRUCTION OF MULTI-PURPOSE 4 STOREY - BUILDING, E. RODRIGUEZ SR. ELEMENTARY SCHOOL, BRGY. E. RODRIGUEZ, QUEZON CITY

CONSTRUCTION OF MULTI-PURPOSE 4 STOREY - BUILDING, E. RODRIGUEZ SR. ELEMENTARY SCHOOL, BRGY. E. RODRIGUEZ, QUEZON CITY is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱39,589,167.74. Status: Reported complete (DPWH). Contractor on record: MANCOL CONST CORP. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures at Brgy. Pasong Tamo, Quezon City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-23-0027032

₱10,268,343.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱39,589,167.74

Progress

Reported complete (DPWH)

Start Date

April 13, 2023

Target End

July 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.