Roads17GJ0011

REHABILITION OF MOLO BOULEVARD ROAD K0005+423-K0006+885, K0008+352-K0009+471

REHABILITION OF MOLO BOULEVARD ROAD K0005+423-K0006+885, K0008+352-K0009+471 is a DPWH-tracked public work in Iloilo City DEO, Region VI. Reported contract value: ₱39,967,467.08. Status: Reported complete (DPWH). Contractor on record: EAST ASIA CONST INC. Figures trace to dpwh.

Iloilo City DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 77%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Jarao Flood Control Project, Particion, Guimbal, Iloilo
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Iloilo City DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱39,967,467.08

Progress

Reported complete (DPWH)

Start Date

February 27, 2017

Target End

September 6, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.