Construction of Flood Mitigation Structure23IM0068

Construction of Flood Control Structure, Phase 3, Camansihay, Tacloban City, Leyte

Construction of Flood Control Structure, Phase 3, Camansihay, Tacloban City, Leyte is a DPWH-tracked public work in TACLOBAN CITY (CAPITAL) (LEYTE), LEYTE, Region VIII. Reported contract value: ₱96,096,604.90. Status: Reported complete (DPWH). Contractor on record: JELM CONST CORP. Figures trace to sumbong.

TACLOBAN CITY (CAPITAL) (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay 103, Palanog, Tacloban City, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-23-0027032

₱10,268,343.00 · FY2023

Released to Siquijor State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,096,604.90

Progress

Reported complete (DPWH)

Start Date

May 23, 2023

Target End

February 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.