Roads22KA0110

CONCRETING OF SITIO KILANG TO SITIO OLD LURUGAN, BRGY. LURUGAN FMR, BRGY. LURUGAN, VALENCIA CITY, BUKIDNON, BRGY. LURUGAN FMR, BRGY. LURUGAN, VALENCIA CITY, BUKIDNON 4TH LD

CONCRETING OF SITIO KILANG TO SITIO OLD LURUGAN, BRGY. LURUGAN FMR, BRGY. LURUGAN, VALENCIA CITY, BUKIDNON, BRGY. LURUGAN FMR, BRGY. LURUGAN, VALENCIA CITY, BUKIDNON 4TH LD is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱11,938,486.76. Status: Reported complete (DPWH). Contractor on record: MAFIL BUILDERS INC. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Brgy. Kalagangan, Sta. 0+200 - Sta. 0+500 (RS) and Sta. 0+400 - Sta. 0+600 (LS), San Fernando, Bukidnon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-22-0006383

₱0.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱11,938,486.76

Progress

Reported complete (DPWH)

Start Date

March 23, 2022

Target End

September 3, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.