Bridges25HN0129

SSP: SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF REVETMENT WALL ALONG BUTUANON RIVER, BARANGAY CASUNTINGAN - BARANGAY CABANCALAN (PHASE 9), MANDAUE CITY, CEBU

SSP: SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF REVETMENT WALL ALONG BUTUANON RIVER, BARANGAY CASUNTINGAN - BARANGAY CABANCALAN (PHASE 9), MANDAUE CITY, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱24,970,168.00. Status: Reported complete (DPWH). Contractor on record: MUANA CONST AND DEVELOPMENT CORP FORMERLY. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cansaga River, Barangay Tilhaong, Consolacion, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-25-0008820

₱2,391,464,863.61 · FY2025

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

261 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS - CONST. OF FLOOD MITIGATION STRUCTURE ALONG GABAYAN RIVER, CANDIJAY, BOHOL, STA. 0+600.00 - STA. 1+068.00, S

Bohol 3rd DEO, Region VII

2025₱144.7M
Past target date (DPWH On-Going)

Construction of Tumuran - Sarangani River Control, Phase II, Candijay, Bohol

CANDIJAY (BOHOL), BOHOL, Region VII

2024₱144.6M
Reported complete (DPWH)
No sat.

CSSP, CONST./IMPROVEMENT OF VARIOUS INFRA IN SUPPORT OF NATIONAL SECURITY(TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAN AT SEGURIDAD PROGRAM-TIKAS), REHAB. OF 47TH INFANTRY (K) BATTALION HEADQUARTERS-CAMP RAJAH SIKATUNA (PHASE 1),BRGY.KATIPUNAN, CARMEN, BOHOL

Region VII, Region VII

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CSSP, CONST./IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAN AT SEGURIDAD PROGRAM-TIKAS), REHAB. OF 47TH INFANTRY (K) BATTALION HEADQUARTERS-CAMP RAJAH SIKATUNA (PHASE 2), BRGY. KATIPUNAN,

Region VII, Region VII

2025₱141.9M
Past target date (DPWH On-Going)

Construction of Wahig River Control Structure, Pamacsalan Area, Pilar, Bohol

PILAR (BOHOL), BOHOL, Region VII

2024₱130.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING), BRGY. POBLACION, CANDIJAY, BOHOL

Bohol 3rd DEO, Region VII

2023₱99.0M
Reported complete (DPWH)
View all 261 projects →

4. Implementation

Contract Amount

₱24,970,168.00

Progress

Reported complete (DPWH)

Start Date

June 3, 2025

Target End

November 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.