Unprogrammed Appropriations 202423K00318

CONSTRUCTION OF DAMULOG-BAGOR-KADINGILAN BY-PASS ROAD, PACKAGE 4, BUKIDNON

CONSTRUCTION OF DAMULOG-BAGOR-KADINGILAN BY-PASS ROAD, PACKAGE 4, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱188,832,119.37. Status: Past target date (DPWH On-Going). Contractor on record: M MONTESCLAROS ENT INC 6506. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱188,832,119.37

Progress

Past target date (DPWH On-Going)

Start Date

December 26, 2024

Target End

April 19, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.