Buildings and Facilities17DO0144

CONSTRUCTION OF FOUR (4) STOREY TWENTY (20) CLASSROOM SCHOOL BUILDING AT MANGGAHAN ES, RODRIGUEZ (MONTALBAN), RIZAL

CONSTRUCTION OF FOUR (4) STOREY TWENTY (20) CLASSROOM SCHOOL BUILDING AT MANGGAHAN ES, RODRIGUEZ (MONTALBAN), RIZAL is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱44,025,349.92. Status: Reported complete (DPWH). Contractor on record: ALPHA. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱44,025,349.92

Progress

Reported complete (DPWH)

Start Date

January 9, 2018

Target End

September 20, 2018