Flood Control and Drainage24K00039

CONSTRUCTION OF FLOOD MITIGATING STRUCTURE ALONG VALENCIA BY-PASS ROAD, UPPER MALINGON BRIDGE, VALENCIA CITY, BUKIDNON

CONSTRUCTION OF FLOOD MITIGATING STRUCTURE ALONG VALENCIA BY-PASS ROAD, UPPER MALINGON BRIDGE, VALENCIA CITY, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱42,498,736.95. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱42,498,736.95

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 4, 2024

Target End

December 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.