Flood Control and Drainage24BH0297

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BUCAL NORTE FLOOD CONTROL STRUCTURE, SECTION 3, DINAPIGUE, ISABELA

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BUCAL NORTE FLOOD CONTROL STRUCTURE, SECTION 3, DINAPIGUE, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱96,306,713.37. Status: Past target date (DPWH On-Going). Contractor on record: GACUTAN CONST INC FORMERLY: GACUTAN CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Digumased, Dinapigue, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-24-0003283

₱-100,791,800.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,306,713.37

Progress

Past target date (DPWH On-Going)

Start Date

October 4, 2024

Target End

December 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.