GAA 2025 SSP25KA0035

INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG JCT SH AGLAYAN-ZAMBOANGUITA RD - K1518 + 000 - K1536 + 000BRGY. AGLAYAN, MALAYBALAY CITY - BRGY. LAMBAGAN, CABANGLASAN, BUKIDNON 2ND LD

INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG JCT SH AGLAYAN-ZAMBOANGUITA RD - K1518 + 000 - K1536 + 000BRGY. AGLAYAN, MALAYBALAY CITY - BRGY. LAMBAGAN, CABANGLASAN, BUKIDNON 2ND LD is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱64,177,732.68. Status: Past target date (DPWH On-Going). Contractor on record: LONG ISLAND BUILDERS. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Miglamin, Malaybalay City, Bukidnon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-25-0016057

₱8,442,625.26 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

275 projects · ₱5.6B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PULIRAN RIVER, PULIRAN BR. SECTION PACKAGE 2, SIBUCO, ZAMBOANGA DEL NORTE

Region IX, Region IX

2024₱164.0M
Past target date (DPWH On-Going)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY BALAKAN-BARANGAY CALUCAP ROAD, SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2025₱153.0M
Past target date (DPWH On-Going)

CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (DOWNSTREAM), SIOCON, ZAMBOANGA DEL NORTE, PACKAGE 2

Region IX, Region IX

2024₱137.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SALUG RIVER AT SALUG BR. SECTION (B00528MN) ALONG SINDANGAN-LILOY ROAD (S01142MN), SALUG, ZAMBOANGA DEL NORTE, PACKAGE 1

Region IX, Region IX

2024₱128.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ESPLANADE AT SALUG BRIDGE (B00528MN), SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2023₱109.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER, GUTALAC, ZAMBOANGA DEL NORTE (UPSTREAM) STA. 0 + 204 - 0 + 604

Zamboanga del Norte 3rd DEO, Region IX

2024₱95.5M
Reported complete (100% progress, DPWH status On-Going)
View all 275 projects →

4. Implementation

Contract Amount

₱64,177,732.68

Progress

Past target date (DPWH On-Going)

Start Date

March 24, 2025

Target End

December 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.