Buildings and Facilities20CH0059

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), HOLY FAMILY VILLAGE ELEMENTARY SCHOOL, BRGY. DILA-DILA, STA. RITA, PAMPANGA

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), HOLY FAMILY VILLAGE ELEMENTARY SCHOOL, BRGY. DILA-DILA, STA. RITA, PAMPANGA is a DPWH-tracked public work in Pampanga 2nd DEO, Region III. Reported contract value: ₱2,866,372.43. Status: Reported complete (DPWH). Contractor on record: WILCU CONST 33992. Figures trace to dpwh.

Pampanga 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-20-0005067

₱3,596,871.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 33992

35 projects · ₱718.9M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF 4 STOREY 20 CLASSROOMS & 4 STOREY 8 CLASSROOMS AT CANLALAY ES, BIÑAN CITY, LAGUNA

Laguna 2nd DEO, Region IV-A

2017₱69.2M
Reported complete (DPWH)
No sat.

PACKAGE 3- A. CONSTRUCTION OF 3 STOREY, 9 CLASSROOM SCHOOL BUILDING AT TALTAL NATIONAL HIGH SCHOOL, MASINLOC, ZAMBALES -BUILDING 1; B. CONSTRUCTION OF 3 STOREY, 9 CLASSROOM SCHOOL BUILDING AT TALTAL NATIONAL HIGH SCHOOL, MASINLOC, ZAMBALES

Zambales 1st DEO, Region III

2017₱47.4M
Reported complete (DPWH)
No sat.

PACKAGE 2- A. CONSTRUCTION OF 4 STOREY, 16 CLASSROOM SCHOOL BUILDING AT LOCLOC NATIONAL HIGH SCHOOL, PALAUIG, ZAMBALES; B. CONSTRUCTION OF 2 STOREY, 6 CLASSROOM SCHOOL BUILDING AT BATO ELEMENTARY SCHOOL, PALAUIG, ZAMBALES

Zambales 1st DEO, Region III

2017₱47.1M
Reported complete (DPWH)
No sat.

PACKAGE 3- A. CONSTRUCTION OF 2 STOREY, 8 CLASSROOM SCHOOL BUILDING AT SAN JUAN ELEMENTARY SCHOOL, BOTOLAN, ZAMBALES; B. CONSTRUCTION OF 2 STOREY, 4 CLASSROOM SCHOOL BUILDING AT SAN ISIDRO ELEMENTARY SCHOOL, BOTOLAN, ZAMBALES

Zambales 1st DEO, Region III

2017₱45.3M
Reported complete (DPWH)
No sat.

PACKAGE 2- A. CONSTRUCTION OF 4 STOREY, 16 CLASSROOM SCHOOL BUILDING AT PAMIBIAN INTEGRATED SCHOOL, CANDELARIA, ZAMBALES; B. CONSTRUCTION OF 1 STOREY, 3 CLASSROOM SCHOOL BUILDING AT LAUIS ELEMENTARY SCHOOL, CANDELARIA, ZAMBALES BUILDING 1)

Zambales 1st DEO, Region III

2017₱43.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FOUR-STOREY (12 CLASSROOM) SCHOOL BUILDING BECURAN NATIONAL HIGH SCHOOL, STA. RITA, PAMPANGA

Pampanga 2nd DEO, Region III

2017₱41.7M
Reported complete (DPWH)
View all 35 projects →

4. Implementation

Contract Amount

₱2,866,372.43

Progress

Reported complete (DPWH)

Start Date

September 30, 2020

Target End

November 28, 2020

5. Audit