Construction of Flood Mitigation Structure24BK0056

Construction of Addalam River Flood Control, Downstream (Disiluad Section), Aglipay, Quirino

Construction of Addalam River Flood Control, Downstream (Disiluad Section), Aglipay, Quirino is a DPWH-tracked public work in AGLIPAY (QUIRINO), QUIRINO, Region II. Reported contract value: ₱33,265,659.77. Status: Reported complete (DPWH). Contractor on record: A P D CONST INC FORMERLY: APD CONST. Figures trace to sumbong.

AGLIPAY (QUIRINO), QUIRINO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Addalam River Flood Control, Downstream ( Disiluad Section ) , Aglipay, Quirino
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010645

₱1,882,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0001012

₱246,761.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018105

₱80,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0001013

₱28,303.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010670

₱174,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

NCA NCA-ROV-24-0004447

₱9,492,576.00 · FY2024

Released to Quirino District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

355 projects · ₱12.1B total · 1 flags

Other projects by this contractor

No sat.

NETWORK DEV'T PROGRAM: CONST'N OF MISSING LINKS/NEW ROADS JCT. VICTORIA-MADDELA-ALICIA-KASIBU, NUEVA VIZCAYA ROAD, QUIRINO, STA. 0+000-STA. 4+500, AGLIPAY, QUIRINO

Region II, Region II

2018₱185.7M
Reported complete (DPWH)
No sat.

OO 1. NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROAD-JCT. ABBAG-GUINGIN BOUNDARY ROAD (BUCAO-LA CONWAP SECTION) QUIRINO, STA. 0+000-STA. 3+040 (CONCRETING, STA. 3+320-STA. 4+240 (OPENING), QUIRINO LONE DISTRICT

Region II, Region II

2018₱166.7M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - ARITAO-QUIRINO ROAD, PACKAGE 1, QUIRINO

Region II, Region II

2024₱158.9M
Reported complete (DPWH)
No sat.

MFO 1: NAT'L ROAD NETWORK SERVICES: NETWORK DEV'T: CONST'N OF MISSING GAPS CONNECTING NAT'L ROADS INCLUDING ROW, JCT. ABBAG-GUINGIN BDRY. ROAD (BUCAO-LA CONWAP SECTION) INCLUDING SLOPE PROTECTION, STA. 000+000-STA.001+680, STA. 002+220-STA.003+770, NAGTIP

Region II, Region II

2017₱142.0M
Reported complete (DPWH)
No sat.

MFO 3:MAINTENANCE AND CONSTRUCTION SERVICES OF OTHER INFRASTRUCTURES: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS-TO DECLARED TOURISM DESTINATIONS-NRJ GUNDAWAY-SUSONG DALAGA, ZAMORA SAN MARCOS-

Region II, Region II

2017₱141.7M
Reported complete (DPWH)
No sat.

MFO 1: NAT'L RD. NETWORK SERVICES: RD. UPGRADING(UNPAVED TO PAVED) BASED ON GRAVEL RD. STRATEGIES, TRAFIC BENCHMARK FOR UPGRADING TO PAVED RD. STANDARD(HDM 4-PROJ.ANALYSIS),TERTIARY RD., JCT. ABBAG-GUINGIN BDRY. RD.

Region II, Region II

2017₱133.8M
Reported complete (DPWH)
View all 355 projects →

4. Implementation

Contract Amount

₱33,265,659.77

Progress

Reported complete (DPWH)

Start Date

April 24, 2024

Target End

November 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.