Bridges20GD0022

WIDENING OF BRIDGE - CALITAN BRIDGE (B00243PN) ALONG ILOILO EAST COAST - CAPIZ ROAD

WIDENING OF BRIDGE - CALITAN BRIDGE (B00243PN) ALONG ILOILO EAST COAST - CAPIZ ROAD is a DPWH-tracked public work in Capiz 1st DEO, Region VI. Reported contract value: ₱10,779,914.60. Status: Reported complete (DPWH). Contractor on record: KIRSKAT VENTURE 32042. Figures trace to dpwh.

Capiz 1st DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱10,779,914.60

Progress

Reported complete (DPWH)

Start Date

February 13, 2020

Target End

October 29, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.