Roads19CA0107

CONCRETING OF SABATAN ROAD, BARANGAY SABANG FMR, BARANGAY SABANG, MORONG, BATAAN

CONCRETING OF SABATAN ROAD, BARANGAY SABANG FMR, BARANGAY SABANG, MORONG, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱4,833,858.00. Status: Reported complete (DPWH). Contractor on record: PASCAL CONST 34168. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,833,858.00

Progress

Reported complete (DPWH)

Start Date

October 14, 2019

Target End

January 11, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.