Buildings and Facilities24DD0102

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. SALABAN I, IBAAN, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. SALABAN I, IBAAN, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱7,684,242.63. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: LLEB CONST AND TRADING. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bawi and Banaba Creek, Padre Garcia, Batangas
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0019178

₱0.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱7,684,242.63

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 7, 2024

Target End

July 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.