GAA 2025 OO-225KF0047

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTIONOF DIKES ALONG BARANGAY PILI, SAPAD, (TRIBUTARY TO MARANDING RIVER), LANAO DEL NORTE

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTIONOF DIKES ALONG BARANGAY PILI, SAPAD, (TRIBUTARY TO MARANDING RIVER), LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱85,763,587.74. Status: Past target date (DPWH On-Going). Contractor on record: AL HUSSEIN CONST. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Sagadan Bridge (B00961MN), Package 1, Tubod, Lanao del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-25-0015168

₱201,394,041.00 · FY2025

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱85,763,587.74

Progress

Past target date (DPWH On-Going)

Start Date

February 24, 2025

Target End

January 5, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.