Roads22LB0190

CONSTRUCTION OF ROAD, SITIO SALUKADANG, BRGY. MAPULA GOING TO BRGY. MALABOG, PAQUIBATO DISTRICT, DAVAO CITY

CONSTRUCTION OF ROAD, SITIO SALUKADANG, BRGY. MAPULA GOING TO BRGY. MALABOG, PAQUIBATO DISTRICT, DAVAO CITY is a DPWH-tracked public work in Davao City DEO, Region XI. Reported contract value: ₱47,529,942.71. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RELY CONST. Figures trace to dpwh.

Davao City DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bago Creek Flood Control Structure, Barangay Bago Gallera, Davao City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-22-0012901

₱542,054.00 · FY2022

Released to Mauaque High School (resettlement school) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱47,529,942.71

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 31, 2022

Target End

March 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.