GAA 2022 OO-222G00148

CONSTRUCTION OF SLOPE PROTECTION WORK ALONG DUNGON CREEK, ILOILO CITY

CONSTRUCTION OF SLOPE PROTECTION WORK ALONG DUNGON CREEK, ILOILO CITY is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱162,884,925.74. Status: Past target date (DPWH On-Going). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱162,884,925.74

Progress

Past target date (DPWH On-Going)

Start Date

March 29, 2022

Target End

February 18, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.