Buildings and Facilities17PL0115

RENOVATION/REPAIR OF CALANAN RHU II

RENOVATION/REPAIR OF CALANAN RHU II is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱1,287,882.01. Status: Reported complete (DPWH). Contractor on record: KALINGA BUILDERS. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0018250

₱291,777.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

25 projects · ₱264.4M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT OF POBLACION TINGLAYAN-TULGAO EAST-TULGAO WEST IN SUPPORT OF PROCESSED FOOD INDUSTRY, BLACKSMITH INDUSTRY AND RATTAN/BAMBOO WEAVING INDUSTRY, TINGLAYAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2018₱33.4M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCH MARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG BALBALAN-PINUKPUK ROAD

Lower Kalinga DEO, Cordillera Administrative Region

2016₱26.2M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG MT. PROVINCE BDRY.-CALANAN-PINUKPUK-ABBUT RD.

Upper Kalinga DEO, Cordillera Administrative Region

2018₱25.2M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION REHABILITATION OF NATIONAL ROADS - REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG MT. PROVINCE BDRY - CALANAN - PINUKPUK - ABBUT RD. (CAGALUAN - CALANAN SECTION S00601LZ) ROAD (CAGALUAN

Upper Kalinga DEO, Cordillera Administrative Region

2017₱23.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE- LUBUAGAN - BATONG BUHAY - ABRA BOUNDARY ROAD

Upper Kalinga DEO, Cordillera Administrative Region

2017₱21.8M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG BALBALAN-PINUKPUK ROAD

Lower Kalinga DEO, Cordillera Administrative Region

2017₱20.6M
Reported complete (DPWH)
View all 25 projects →

4. Implementation

Contract Amount

₱1,287,882.01

Progress

Reported complete (DPWH)

Start Date

August 14, 2017

Target End

November 11, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.