Roads17FK0018

OFF-CARRIAGEWAY IMPV'T. INCLUDING DRAINAGE-TERTIARY ROADS-BACON-SAWANGA-PTO. DIAZ ROAD, KO592+071-KO592+235, KO595+460+KO595+770, KO597+000-KO597+190, KO597+320-KO598+714, KO610+000-KO610+370, KO610+810-KO611+767, BACON DIST., SORSOGON CITY

OFF-CARRIAGEWAY IMPV'T. INCLUDING DRAINAGE-TERTIARY ROADS-BACON-SAWANGA-PTO. DIAZ ROAD, KO592+071-KO592+235, KO595+460+KO595+770, KO597+000-KO597+190, KO597+320-KO598+714, KO610+000-KO610+370, KO610+810-KO611+767, BACON DIST., SORSOGON CITY is a DPWH-tracked public work in Sorsogon DEO, Region V. Reported contract value: ₱27,023,772.00. Status: Reported complete (DPWH). Contractor on record: STEVEN CONST. Figures trace to dpwh.

Sorsogon DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Osiao Flood Control, Bacon District, Sorsogon City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Sorsogon DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

252 projects · ₱7.4B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES ALONG TAGAYTAY RIVER, BRGY. TAGAYTAY-BARIW, CAMALIG, ALBAY, CAMALIG, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱164.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 - PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF LEFT AND RIGHT SIDE UGSONG RIVER FLOOD CONTROL STRUCT

Albay 3rd DEO, Region V

2025₱138.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-MATNOG-BULAN-MAGALLANES WEST COAST HIGHWAY, SORSOGON PACKAGE I MAGALLANES, SORSOGON

Sorsogon DEO, Region V

2022₱108.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-MATNOG-BULAN-MAGALLANES WEST COAST HIGHWAY, SORSOGON PACKAGE II, MAGALLANES, SORSOGON

Sorsogon DEO, Region V

2022₱106.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-MATNOG-BULAN-MAGALLANES WEST COAST HIGHWAY, SORSOGON PACKAGE I MAGALLANES, SORSOGON

Sorsogon DEO, Region V

2021₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-ACCESS ROAD LEADING TO SORSOGON CITY PORT, SORSOGON

Sorsogon DEO, Region V

2023₱93.6M
Reported complete (DPWH)
View all 252 projects →

4. Implementation

Contract Amount

₱27,023,772.00

Progress

Reported complete (DPWH)

Start Date

March 9, 2017

Target End

September 4, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.