Water Provision and Storage18DO0094

CONSTRUCTION/REHABILITATION OF WATER SUUPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS-RAINWATER COLLECTORS SYSTEM AT 1. SAN MATEO ELEMENTARY SCHOOL 2. GUITNANGBAYAN ELEMENTARY SCHOOL, 3. SAN MATEO NATIONAL HIGH SCHOOL 4. DULONG BAYAN I ELEMENTARY ...

CONSTRUCTION/REHABILITATION OF WATER SUUPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS-RAINWATER COLLECTORS SYSTEM AT 1. SAN MATEO ELEMENTARY SCHOOL 2. GUITNANGBAYAN ELEMENTARY SCHOOL, 3. SAN MATEO NATIONAL HIGH SCHOOL 4. DULONG BAYAN I ELEMENTARY ... is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱3,150,461.65. Status: Reported complete (DPWH). Contractor on record: F V SANGALANG CONST 37083. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,150,461.65

Progress

Reported complete (DPWH)

Start Date

May 2, 2018

Target End

June 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.