Water Provision and Storage21JI0059

CONSTRUCTION OF WATER MANAGEMENT FACILITY, BARANGAY GANDIANGAN, IMELDA, ZAMBOANGA SIBUGAY

CONSTRUCTION OF WATER MANAGEMENT FACILITY, BARANGAY GANDIANGAN, IMELDA, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 1st DEO, Region IX. Reported contract value: ₱2,964,973.90. Status: Reported complete (DPWH). Contractor on record: JAYKRIS ENT. Figures trace to dpwh.

Zamboanga Sibugay 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of flood control for prevention and mitigation along Barangay San Jose part of Sibuguey River, Imelda, Zamboanga Sibugay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱392,621,000.00 · FY2021

Released to Batangas 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

105 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱2,964,973.90

Progress

Reported complete (DPWH)

Start Date

March 22, 2021

Target End

June 19, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.