Roads25DC0032

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY SAN GABRIEL, LAUREL, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY SAN GABRIEL, LAUREL, BATANGAS is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱4,949,234.80. Status: Reported complete (DPWH). Contractor on record: NDA BUILDERS AND DEVELOPERS. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay San Roque, Bauan, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-25-0008577

₱372,885.00 · FY2025

Released to Ilocos Training and Regional Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Contractor

101 projects · ₱1.3B total · 2 flags

Other projects by this contractor

View all 101 projects →

4. Implementation

Contract Amount

₱4,949,234.80

Progress

Reported complete (DPWH)

Start Date

February 12, 2025

Target End

June 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.