Water Provision and Storage20HJ0063

LOCAL INFRASTRUCTURE PROGRAM-WATER MANAGEMENT FACILITIES-CONSTRUCTION OF WATER SYSTEM AT BRGY. SANDAYAO AND BRGY. TACPAO, GUIHULNGAN CITY NEGROS ORIENTAL

LOCAL INFRASTRUCTURE PROGRAM-WATER MANAGEMENT FACILITIES-CONSTRUCTION OF WATER SYSTEM AT BRGY. SANDAYAO AND BRGY. TACPAO, GUIHULNGAN CITY NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱1,980,000.00. Status: Reported complete (DPWH). Contractor on record: KOUKEN CONST. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-20-0000998

₱1,730,697.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

112 projects · ₱1.8B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (JCT BAIS-KABANKALAN-NEGROS OCC BDRY) - K0118 + 400 - K0120 + 300, GUIHULNGAN CITY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱106.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING ALONG PRIMARY ROAD-DUMAGUETE NORTH ROAD (JCT. BAIS-KABANKALAN-NEGROS OCC BDRY) K0114+194 - K0116+580, GUIHULNGAN CITY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱101.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM/NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (JCT BAIS - KABANKALAN - NEGROS OCC BDRY) - K0104 + 828 - K0107 + 303, LA LIBERTAD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2023₱94.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (JCT BAIS - KABANKALAN - NEGROS OCC BDRY) - K110+000 - K112+480, GUIHULNGAN CITY

Negros Oriental 1st DEO, Negros Island Region

2024₱71.1M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (JCT BAIS - KABANKALAN - NEGROS OCC BDRY) - K0107 + 875 -K0109+754, K0109+792-K0110+000, LA LIBERTAD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2024₱68.0M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF ROADS, BARANGAY NASUNGGAN - AYA ROAD, LA LIBERTAD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2024₱48.5M
Reported complete (DPWH)
View all 112 projects →

4. Implementation

Contract Amount

₱1,980,000.00

Progress

Reported complete (DPWH)

Start Date

October 20, 2020

Target End

December 11, 2020

5. Audit