Flood Control and Drainage25CK0082

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG THE BANKS OF RIO CHICO RIVER IN BARANGAY LOMBOY (PHASE VII), LA PAZ, TARLAC

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG THE BANKS OF RIO CHICO RIVER IN BARANGAY LOMBOY (PHASE VII), LA PAZ, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱93,092,065.36. Status: Past target date (DPWH On-Going). Contractor on record: A C SOLIVEN CONST. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure (Phase III), La Paz, Tarlac
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-25-0014403

₱153,036.00 · FY2025

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱93,092,065.36

Progress

Past target date (DPWH On-Going)

Start Date

June 13, 2025

Target End

December 13, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.