Flood Control and Drainage23IC0172

CONSTRUCTION OF EMBARKADERO FLOOD CONTROL ALONG BAHAY RIVER, PALO, LEYTE

CONSTRUCTION OF EMBARKADERO FLOOD CONTROL ALONG BAHAY RIVER, PALO, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱47,526,250.00. Status: Reported complete (DPWH). Contractor on record: JJ PALACIO CONST. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bangon River, Brgy. Arado, Palo, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-23-0020492

₱1,131,522.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱47,526,250.00

Progress

Reported complete (DPWH)

Start Date

March 25, 2024

Target End

October 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.