Flood Control and Drainage25EB0055

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PINAMANAAN RIVER, PHASE 1, BARANGAY MANGARIN, SAN JOSE, OCCIDENTAL MINDORO

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PINAMANAAN RIVER, PHASE 1, BARANGAY MANGARIN, SAN JOSE, OCCIDENTAL MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱48,699,086.47. Status: Reported complete (DPWH). Contractor on record: MIGHTY DRAGON BUILDERS INC. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Pinamanaan River, Phase 1, Barangay Mangarin, San Jose, Occidental Mindoro
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0014153

₱121,138.00 · FY2025

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,699,086.47

Progress

Reported complete (DPWH)

Start Date

February 26, 2025

Target End

September 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.