Flood Control and Drainage24CD0314

REHABILITATION OF DISASTER RELATED INFRASTRUCTURE AND OTHER FACILITIES REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG TUMANA SAN GABRIEL, STA. MARIA, BULACAN

REHABILITATION OF DISASTER RELATED INFRASTRUCTURE AND OTHER FACILITIES REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG TUMANA SAN GABRIEL, STA. MARIA, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱18,717,097.24. Status: Reported complete (DPWH). Contractor on record: JB CONST AND SUPPLY INC FORMERLY:JB CONST AND SUPPLY. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sta. Maria River, Sta. 04 + 900 - Sta. 05 + 050 ( Poblacion - Macaiban Section ) , Santa Maria, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0018833

₱7,150,000.00 · FY2024

Released to Surigao del Norte State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱18,717,097.24

Progress

Reported complete (DPWH)

Start Date

February 21, 2025

Target End

August 13, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.