Buildings and Facilities25IN0048

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY STO. NIÑO, SAN JUAN, SOUTHERN LEYTE

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY STO. NIÑO, SAN JUAN, SOUTHERN LEYTE is a DPWH-tracked public work in Southern Leyte 2nd DEO, Region VIII. Reported contract value: ₱2,959,184.56. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: TUBIGAN BUILDERS. Figures trace to dpwh.

Southern Leyte 2nd DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Protection Work of Dam, Tam-is Communal Irrigation System, Maasin City, Southern Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-25-0015072

₱11,427,513.00 · FY2025

Released to Southern Leyte 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱2,959,184.56

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 11, 2025

Target End

July 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.