Buildings: Construction - without Piles - Low Rise - Concrete (Frame) (1 to 5 Storeys)25KN0063

COMPLETION/UPGRADING/REPAIR AND EQUIPPING OF RHU/SHC, VALENCIA CITY HEALTH OFFICE, BUKIDNON

COMPLETION/UPGRADING/REPAIR AND EQUIPPING OF RHU/SHC, VALENCIA CITY HEALTH OFFICE, BUKIDNON is a DPWH-tracked public work in Bukidnon 4th DEO, Region X. Reported contract value: ₱0.00. Status: Ongoing (DPWH-reported) (For Procurement (DPWH-reported)). Contractor on record: Contractor not linked in this database. Figures trace to dpwh.

Bukidnon 4th DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Jct SH-Manolo Fortich-Libona-Indahag Road, (Upstream and Downstream) of Sta. Fe Bridge, Libona, Bukidnon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-25-0003247

₱182,153.00 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱0.00

Progress

For Procurement (DPWH-reported)

Start Date

Data not yet available

Target End

Data not yet available

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.