Roads21FB0195

CONCRETING OF BRGY. BUYO FMR, BRGY. BUYO, MANITO, ALBAY

CONCRETING OF BRGY. BUYO FMR, BRGY. BUYO, MANITO, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱12,020,356.75. Status: Past target date (DPWH On-Going). Contractor on record: ENM CONST. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱37,600,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System, Brgy. Buyo, Manito, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-21-0009333

₱2,743,969.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱12,020,356.75

Progress

Past target date (DPWH On-Going)

Start Date

August 9, 2021

Target End

December 6, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.