Flood Control and Drainage25AA0478

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF SEAWALL, BARANGAY NALVO, PASUQUIN, ILOCOS NORTE

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF SEAWALL, BARANGAY NALVO, PASUQUIN, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱47,021,762.62. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: LINEAR CONST CORP. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Calioet-Libong, Bacarra, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-25-0008479

₱38,977,790.00 · FY2025

Released to Ilocos Norte 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,021,762.62

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 17, 2025

Target End

September 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.