Roads17CB0071

CONCRETING OF UPPER DANGCOL FMR, BRGY. DANGCOL, BALANGA, BATAAN

CONCRETING OF UPPER DANGCOL FMR, BRGY. DANGCOL, BALANGA, BATAAN is a DPWH-tracked public work in Bataan 2nd DEO, Region III. Reported contract value: ₱4,972,827.45. Status: Reported complete (DPWH). Contractor on record: VF CONST. Figures trace to dpwh.

Bataan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,972,827.45

Progress

Reported complete (DPWH)

Start Date

June 14, 2017

Target End

September 13, 2017

5. Audit