GAA 2025 SSP25EB0073

CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY SAN VICENTE, SABLAYAN, OCCIDENTAL MINDORO

CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY SAN VICENTE, SABLAYAN, OCCIDENTAL MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱5,762,780.62. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: F A TORRES CONST. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Caminawit, San Jose, Occidental Mindoro
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0014153

₱121,138.00 · FY2025

Released to Davao del Norte State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱5,762,780.62

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 19, 2025

Target End

August 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.