Bridges23F00385

ORGANIZATIONAL OUTCOME 1 (OO1): ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-CONSTRUCTION OF NEW BRIDGES-CONSTRUCTION OF PAMBUHAN BRIDGE, MERCEDES, CAMARINES NORTE, MERCEDES, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT)

ORGANIZATIONAL OUTCOME 1 (OO1): ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-CONSTRUCTION OF NEW BRIDGES-CONSTRUCTION OF PAMBUHAN BRIDGE, MERCEDES, CAMARINES NORTE, MERCEDES, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱33,774,993.69. Status: Reported complete (DPWH). Contractor on record: E P L GEN CONST AND SUPPLY INC 15559. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱33,774,993.69

Progress

Reported complete (DPWH)

Start Date

January 23, 2024

Target End

August 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.