Buildings and Facilities22ME0113

CONST. OF MPB IN BRGY. COLON, MAASIM, SARANGANI

CONST. OF MPB IN BRGY. COLON, MAASIM, SARANGANI is a DPWH-tracked public work in Sarangani DEO, Region XII. Reported contract value: ₱9,743,917.28. Status: Reported complete (DPWH). Contractor on record: JAYSABB CONST AND SUPPLY. Figures trace to dpwh.

Sarangani DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bagacay Bridge Flood Control, Alabel, Sarangani
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-22-0000829

₱666,157.00 · FY2022

Released to Noli National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,743,917.28

Progress

Reported complete (DPWH)

Start Date

June 9, 2022

Target End

June 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.