Roads24HO0019

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF LOOC-GUIWANON ROAD AT BARANGAY LOOC AND GUIWANON, G

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF LOOC-GUIWANON ROAD AT BARANGAY LOOC AND GUIWANON, G is a DPWH-tracked public work in Cebu 7th DEO, Region VII. Reported contract value: ₱9,896,607.25. Status: Reported complete (DPWH). Contractor on record: FIRST GRANDEUR BUILDERS INC FORMERLY: FIRST GRANDEUR BUILDERS. Figures trace to dpwh.

Cebu 7th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment Wall along Talaba River Flood Control, Barangay Canduling, Ronda, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-24-0011737

₱57,620,507.20 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

323 projects · ₱4.1B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MAHANLUD -BAR

Cebu 7th DEO, Region VII

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANGACO ROAD, BARANGAY MA

Cebu 7th DEO, Region VII

2024₱96.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROADS, PALANAS-CANORONG-MANGACO BRGY. ROADS, GINATIL

Cebu 7th DEO, Region VII

2023₱96.5M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT MARIA RIVER (UPSTREAM OF MARIA BRIDGE), PHASE 1, PO

Siquijor DEO, Negros Island Region

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

CSSP: ACCESS ROADS AND/OR BRIDGES FROM THE NATL. ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-IMPROVEMENT OF ROAD WITH DRAINAGE FACILITIES AT AGATON SORONO ST. TO SUBA MASULOG-SUBA PANAS ROAD, BARGY. SUBABASBAS, LAPU-LAPU CITY, CITY

Cebu 6th DEO, Region VII

2023₱96.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONST OF ROAD, BRGY ULING - BRGY TAGJAGUIM

Cebu 1st DEO, Region VII

2025₱91.7M
Past target date (DPWH On-Going)
View all 323 projects →

4. Implementation

Contract Amount

₱9,896,607.25

Progress

Reported complete (DPWH)

Start Date

February 16, 2024

Target End

April 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.