Roads24PF0071

REBLOCKING OF DAMAGED CONCRETE PAVEMENTS ALONG BAGUIO-BONTOC ROAD, K0307+188-K0307+970, K0308+009-K0308+187, K0308+861-K0308+870, K0309+830-K0309+849, K0321+340-K0321+353.5, K0322+107-K0324+636, K0325+592.5+K0325+606, K0326+548-K0326+880, K0327+627-K0327+

REBLOCKING OF DAMAGED CONCRETE PAVEMENTS ALONG BAGUIO-BONTOC ROAD, K0307+188-K0307+970, K0308+009-K0308+187, K0308+861-K0308+870, K0309+830-K0309+849, K0321+340-K0321+353.5, K0322+107-K0324+636, K0325+592.5+K0325+606, K0326+548-K0326+880, K0327+627-K0327+ is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱0.00. Status: Ongoing (DPWH-reported) (For Procurement (DPWH-reported)). Contractor on record: Contractor not linked in this database. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Baguyos CIS Flood Control Structure along Baguyos Creek, Mankayan, Benguet
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-24-0004574

₱2,383,785.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱0.00

Progress

For Procurement (DPWH-reported)

Start Date

Data not yet available

Target End

Data not yet available

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.