Flood Control and Drainage21BH0049

CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL STRUCTURE SINAOANGAN SUR, STA. 0+000 - STA. 0+385

CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL STRUCTURE SINAOANGAN SUR, STA. 0+000 - STA. 0+385 is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: V B MANUBAY CONST 32705. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of Flood Control Structure, Sinaoangan Sur, San Agustin, Isabela, Sta. 0+000 - Sta. 0+385
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Isabela 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 32705

135 projects · ₱2.5B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES - CONSTRUCTION OF PALACIAN FLOOD CONTROL STRUCTURE, SECTION 1, SAN AGUSTIN, ISABELA

Isabela 4th DEO, Region II

2024₱96.5M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF BRGY. MINURI FLOOD CONTROL STRUCTURE, SECTION 4, JONES, ISABELA

Isabela 4th DEO, Region II

2023₱96.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF BRGY. PAPAN WESTE FLOOD CONTROL STRUCTURE, SECTION 3, JONES, ISABELA

Isabela 4th DEO, Region II

2023₱96.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF BRGY. PALAGAO FLOOD CONTROL STRUCTURE, SECTION 3, JONES, ISABELA

Isabela 4th DEO, Region II

2023₱96.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF LAOAG FLOOD CONTROL STRUCTURE SECTION 1, SAN AGUSTIN, ISABELA

Isabela 4th DEO, Region II

2024₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF MAPALAD FLOOD CONTROL STRUCTURE, SECTION 1, SAN AGUSTIN, ISABELA

Isabela 4th DEO, Region II

2024₱96.2M
Past target date (DPWH On-Going)
View all 135 projects →

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 23, 2021

Target End

September 21, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.