Roads23DE0083

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF SOLAR PAVEMENT STUDS ALONG BATANGAS CITY - SAN PASCUAL - BAUAN DIVERSION ROAD (BAUAN AND SAN PASCUAL SECTION).

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF SOLAR PAVEMENT STUDS ALONG BATANGAS CITY - SAN PASCUAL - BAUAN DIVERSION ROAD (BAUAN AND SAN PASCUAL SECTION). is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱101,325,000.00. Status: Reported complete (DPWH). Contractor on record: KEASCIA CONST & SUPPLY. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay San Isidro (Section 1), Batangas City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-23-0020457

₱111,485,938.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱101,325,000.00

Progress

Reported complete (DPWH)

Start Date

April 5, 2023

Target End

September 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.