GAA 2025 OO-125ME0014

REHABILITATION / RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG DEMOLOC - LITTLE BAGUIO - ALABEL RD K1669+080 - K1671+000, ALABEL, SARANGANI PROVINCE

REHABILITATION / RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG DEMOLOC - LITTLE BAGUIO - ALABEL RD K1669+080 - K1671+000, ALABEL, SARANGANI PROVINCE is a DPWH-tracked public work in Sarangani DEO, Region XII. Reported contract value: ₱15,565,203.51. Status: Past target date (DPWH On-Going). Contractor on record: MARDI INFRA BUILDERS. Figures trace to dpwh.

Sarangani DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Molo Creek Flood Control, Alabel, Sarangani
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-25-0014631

₱2,983,776.00 · FY2025

Released to Iloilo 6th District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱15,565,203.51

Progress

Past target date (DPWH On-Going)

Start Date

July 3, 2025

Target End

November 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.