Flood Control and Drainage24CC0641

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY SANTA CRUZ (SITIO TUKLAS), GUIGUINTO, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY SANTA CRUZ (SITIO TUKLAS), GUIGUINTO, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱74,110,545.00. Status: Past target date (DPWH On-Going). Contractor on record: WAWAO BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagbag Creek, Barangay Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000335

₱29,019,605.00 · FY2024

Released to Regional Office - NCR (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

164 projects · ₱9.2B total · 15 flags

4. Implementation

Contract Amount

₱74,110,545.00

Progress

Past target date (DPWH On-Going)

Start Date

February 28, 2025

Target End

September 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.