Buildings and Facilities24NF0087

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CONSOLACION, DAPA, SURIGAO DEL NORTE

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CONSOLACION, DAPA, SURIGAO DEL NORTE is a DPWH-tracked public work in Surigao del Norte 1st DEO, Region XIII. Reported contract value: ₱4,400,939.38. Status: Reported complete (DPWH). Contractor on record: JZL BUILDERS. Figures trace to dpwh.

Surigao del Norte 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tagbayani Flood Mitigation Structure, Barangay Tagbayani, Sison, Surigao del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-24-0014212

₱2,977,141.00 · FY2024

Released to Regional Office - I (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

81 projects · ₱732.4M total · 0 flags

4. Implementation

Contract Amount

₱4,400,939.38

Progress

Reported complete (DPWH)

Start Date

July 29, 2024

Target End

December 25, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.