Buildings and Facilities19EF0127

CONSTRUCTION OF MULTI-PURPOSE BUILDING (OPEN COURT), OCAYAN, BATARAZA, PALAWAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING (OPEN COURT), OCAYAN, BATARAZA, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱978,523.45. Status: Reported complete (DPWH). Contractor on record: MAINTIN CONST. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱978,523.45

Progress

Reported complete (DPWH)

Start Date

September 1, 2019

Target End

November 29, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.