Flood Control and Drainage21PE0012

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER SECTION 30 (BESSANG), STA. 209+880 - STA. 210+380, KABAYAN, BENGUET

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER SECTION 30 (BESSANG), STA. 209+880 - STA. 210+380, KABAYAN, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱9,745,805.43. Status: Reported complete (DPWH). Contractor on record: VANVIN CONST AND SUPPLY. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure within Agno River Basin: along Agno River Section 30 (Bessang), Sta. 209 + 880 - Sta. 210 + 380, Kabayan, Benguet
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱392,621,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱9,745,805.43

Progress

Reported complete (DPWH)

Start Date

March 1, 2021

Target End

August 4, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.