Bridges18IK0073

WIDENING OF PERMANENT BRIDGES, SILAGA BRIDGE ALONG DAANG MAHARLIKA (SM) (SAN ISIDRO - SAN JUANICO BR) (ONE LANE)

WIDENING OF PERMANENT BRIDGES, SILAGA BRIDGE ALONG DAANG MAHARLIKA (SM) (SAN ISIDRO - SAN JUANICO BR) (ONE LANE) is a DPWH-tracked public work in Samar 2nd DEO, Region VIII. Reported contract value: ₱37,231,973.37. Status: Reported complete (DPWH). Contractor on record: FRD CONST. Figures trace to dpwh.

Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱15,336,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Protection Works Structure, Polangi Bridge along Daang Mahalika (SM) (Sn Isidro - Sn Juanico Br)
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Samar 2nd DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱37,231,973.37

Progress

Reported complete (DPWH)

Start Date

July 15, 2018

Target End

February 17, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.